Project |
Goal by End of Fiscal Year |
1 |
Beech Double Crossover |
100% Design complete, w/ Procurement for bidding |
2 |
South Bay 925 Rapid Extension (11 ZEB Infrastructure) |
60% Station Design, 90% SBBMF Infrastructure Layout |
3 |
ZEB Implementation - Phase 1 |
Construction 100% complete |
4 |
ZEB Implementation - Phase 2 |
Construction 100% complete |
5 |
Demolish Pyramid Building |
Construction 25% complete |
6 |
IMT Double Track (Blue to Green) |
100% Design complete, w/ Procurement for bidding |
7 |
Blue Line Substation Replacement |
Construction 75% complete |
8 |
SDIV “F” Street Removal |
Construction 50% complete |
9 |
Additional LPG Storage at Copley Park Division |
Construction 100% complete |
10 |
Mission Valley West Signal Upgrade - Morena to Qualcomm |
Construction 100% complete |
11 |
SDSU Ventilation |
Construction 100% complete |
12 |
Building C Power Supply |
Construction 100% complete |
13 |
Kearny Mesa Division Concrete |
Construction 100% complete |
14 |
Middletown / 9 & 11 |
Middletown - Special Trackwork in San Diego |
15 |
Beyer Blvd - SANDAG |
Construction 25% complete |
16 |
Green Line Substations |
Construction 100% complete |
17 |
Kearny Mesa Division Concrete |
Construction 100% complete |
18 |
Mission Valley Elevator (1 of 2) |
Construction 100% complete |
Department Goals
19 |
Project Management Training |
100% complete |
20 |
Implement Uniform Budget / Schedule Reporting Template |
100% complete |
21 |
Standardize / Centralize Project Files |
100% complete |
22 |
Implement Property Inspection / Maintenance Schedule |
100% complete |
23 |
Develop Permit Procedures and Filing Naming Conventions |
100% complete |
24 |
Define Process for Electronic Permit Applications |
100% complete (concept only) |
25 |
Grade Crossing Modification Database |
100% complete |
26 |
Electronic Access to SANDAG As-Builts |
100% complete |